Palm River Area 1 and 2

Palm River Project map

PALM RIVER – AREAS 1 AND 2
The Palm River project replaces aging water, sewer, and stormwater infrastructure within the Palm River neighborhood along portions of Cypress Way East and Palm River Boulevard, Golfview Drive, Pompano Drive and Eastwood Drive.  The project also includes improvements to two existing wastewater pumping stations. As part of the improvements, water and sewer service lines will be replaced. Clay sewer pipes will be replaced with new PVC pipes. This work may need to take place on private property and permission from the owner will be obtained, as necessary. Rehabilitation of the stormwater collection and treatment system will take place in the right-of-way. All driveways will be restored to their previous condition or better and all roads will be rebuilt. A new sidewalk will be installed along a section of Cypress Way East. This project will ensure a continued high level of utility service for the community.


PROJECT PROGRESS UPDATE
March 15, 2024

New PVC water main, fire hydrants and water services were installed along Cypress Way East, Golfview Drive and Palm River Blvd. The new water main along Saddlebrook lane was also installed and restoration activities related to the new water main were completed in this area.  Water system and services installation activities have been completed along Cypress Way East, Pompano Drive and Eastwood Drive on Phase 2. Existing asbestos-cement water main removal has been completed along Cypress Way East, Palm River Blvd, and Golfview Drive on Phase 1 and continued along Cypress Way East on Phase 2.

New sanitary sewer main and laterals, force main, and stormwater drainage installation have also been completed along Cypress Way East. New sanitary sewer main, laterals, and stormwater drainage installation were finished along Palm River Blvd. and Golfview Drive on Phase 1. Well points were installed, the existing roadway was milled, the existing sanitary sewer main was exposed at the existing Pump Station, and new sanitary sewer main installation activities continued along Cypress Way East on Phase 2.

Road restoration activities were completed along Cypress Way East including restoring driveways, grading the right-of-way, repairing existing irrigation systems and installing new sidewalk.  Paving was completed on January 4, 2024, along Palm River Blvd and road restoration activities continued along Golfview Drive Phase 1.  Asphalt paving along Golfview Drive was completed on February 26, 2024, and driveway restoration activities has commenced. Contractor is currently in the process of grading and sodding the remaining houses along Cypress Way East and restoring driveways along Palm River Blvd. Phase 1 and Golfview Drive.

 

Palm River Public Utility Renewal Project
Phases 1 and 2

Current Progress as of March 15, 2024

Contractor: Haskins, Inc.
Cost: $15,579,339.85
Construction commencement date: March 2023
Anticipated construction completion date: Summer 2024

The projects listed below represent the Palm River projects that are currently under construction, design development or early planning stages. Additional projects will be added to this page as new projects are identified and developed within Palm River program area.

UNDER CONSTRUCTION

Areas as they become under design or under construction, respectively. 

UNDER DESIGN

Areas as they become under design or under construction, respectively. 

COMPLETE