Palm River Area 1 and 2

Palm River Project map

PALM RIVER – AREAS 1 AND 2
The Palm River project replaces aging water, sewer, and stormwater infrastructure within the Palm River neighborhood along portions of Cypress Way East and Palm River Boulevard, Golfview Drive, Pompano Drive and Eastwood Drive.  The project also includes improvements to two existing wastewater pumping stations. As part of the improvements, water and sewer service lines will be replaced. Clay sewer pipes will be replaced with new PVC pipes. This work may need to take place on private property and permission from the owner will be obtained, as necessary. Rehabilitation of the stormwater collection and treatment system will take place in the right-of-way. All driveways will be restored to their previous condition or better and all roads will be rebuilt. A new sidewalk will be installed along a section of Cypress Way East. This project will ensure a continued high level of utility service for the community.


PROJECT PROGRESS UPDATE
January 8, 2025

New PVC water main, fire hydrants and water services were installed along all streets located on Areas 1 and 2.  Existing asbestos-cement water main removal has been completed along Areas 1 and 2.  New sanitary sewer main and laterals, force main, and stormwater drainage installation have also been completed along all streets on Areas 1 and 2. Contractor finished rehabilitating the pump station along Cypress Way East on Area 1 and they finished all work related to the rehabilitation of PS 103.06. Contractor finished grouting the existing sanitary sewer main, force main and stormwater drainage to be abandoned along the entire project and the water main to be abandoned along Saddlebrook Lane. Contractor placed the final lift of asphalt along the entirety of the project and also installed asphalt driveways. Contractor performed the Substantial Completion Walkthrough and addressed all outstanding punch list items along Areas 1 and 2 to finalize the project. This is the last project update.

Palm River Public Utility Renewal Project
Phases 1 and 2

Current Progress as of January 8, 2025

Contractor: Haskins, Inc.
Cost: $15,579,339.85
Construction commencement date: March 2023
Anticipated construction completion date: Winter 2024

The projects listed below represent the Palm River projects that are currently under construction, design development or early planning stages. Additional projects will be added to this page as new projects are identified and developed within Palm River program area.

UNDER CONSTRUCTION

Areas as they become under design or under construction, respectively. 

UNDER DESIGN

Areas as they become under design or under construction, respectively. 

COMPLETE

Areas as they become under design or under construction, respectively.