
98th and 99th AVENUE NORTH PUBLIC UTILITY RENEWAL PROJECT
This project is part of the Naples Park Utility Renewal Project and includes the removal and replacement of water, wastewater and stormwater infrastructure that service residents and businesses along 98th and 99th Avenues North between Tamiami Trail and Vanderbilt Drive. As part of the improvements, the contractor will be replacing water and wastewater service lines. Clay wastewater pipe laterals from the property will be replaced with new PVC pipe. This work may need to take place on private property and permission from the owner will be necessary. Stormwater collection and treatment system rehabilitation work will take place in the right of way. This project will also improve the ability to collect wastewater from Basin 101 for conveyance to the treatment facility to prevent overflows and ensure a continued high level of wastewater service to the community.
PROJECT PROGRESS UPDATE
November 25, 2025
The installation of the Water, Wastewater, and Stormwater infrastructure was completed along both 98th and 99th Avenue North. The restoration of the roads and right-of-way were also completed with a few items left under a warranty period.
This is the last update since the project was finalized.
SYSTEMS INSTALLATION PROGRESS UPDATE
November 25, 2025
98th Avenue North
| Water System | Wastewater Sewer System | Stormwater System | ||||
|---|---|---|---|---|---|---|
| Block | New Water Pipe Installation | Old Water Pipe Removal | New Sewer Main Installation | New Sewer Laterals Installation | Stormwater Installation | Restoration |
| 500 | 100% | 100% | 100% | 100% | 100% | 100% |
| 600 | 100% | 100% | 100% | 100% | 100% | 100% |
| 700 | 100% | 100% | 100% | 100% | 100% | 100% |
| 800 | 100% | 100% | 100% | 100% | 100% | 100% |
99th Avenue North
| Water System | Wastewater Sewer System | Stormwater System | ||||
|---|---|---|---|---|---|---|
| Block | New Water Pipe Installation | Old Water Pipe Removal | New Sewer Main Installation | New Sewer Laterals Installation | Stormwater Installation | Restoration |
| 500 | 100% | 100% | 100% | 100% | 100% | 100% |
| 600 | 100% | 100% | 100% | 100% | 100% | 100% |
| 700 | 100% | 100% | 100% | 100% | 100% | 100% |
| 800 | 100% | 100% | 100% | 100% | 100% | 100% |
Contractor: DN Higgins, Inc.
Cost: $17,862,085.00
Construction commencement date: January 2024
Anticipated construction completion date: December 2025
The projects listed below represent the Basin 101 projects that are currently under construction, design development or early planning stages. Additional projects will be added to this page as new projects are identified and developed within Basin 101 program area.
(CPS – Community Pump Station)