This project is part of the Naples Park Utility Renewal Project and includes the removal and replacement of water, wastewater and stormwater infrastructure that service residents and businesses along 105th and 106th Avenues North between Tamiami Trail and Vanderbilt Drive. As part of the improvements, the contractor will be replacing water and wastewater service lines. Clay wastewater pipe laterals from the property will be replaced with new PVC pipe. This work may need to take place on private property and permission from the owner will be necessary. Stormwater collection and treatment system rehabilitation work will take place in the right of way. This project will also improve the ability to collect wastewater from Basin 101 for conveyance to the treatment facility to prevent overflows and ensure a continued high level of wastewater service to the community.

PROJECT PROGRESS UPDATE
September 13, 2023

The contractor finished installation of new 8-inch PVC water main, fire hydrants and water services along the entirety of 106th Avenue North and finished water services, water meters, and backflow preventers along the 500 and 600 block of 105th Avenue North. The existing asbestos-cement water mains along the 500 block and half of the 600 block of both streets and along the 700 block of 106th Avenue North were also removed and the contractor tied-in the existing 12-inch water main to the new water main at 105th Avenue North and 6th Street North. The contractor also finished water main installation along the 700 and 800 blocks of 105th Avenue North, performed a successful pressure test on the new water main, flushed and chlorinated the new water main, and obtained bacteriological testing results for FDEP Permit Approval. The contractor anticipates connecting the new water services to houses along the 700 and 800 blocks of 105th Avenue North through September 2023 after receiving FDEP Permit approval.

The contractor finished installation of sanitary sewer main and laterals along the 500 block and half of the 600 block of both streets and finished stormwater drainage installation along the 500 block and half of the 600 block of both streets and along 6th Street North. The contractor finished sanitary sewer main and sanitary sewer lateral along the 600 and 700 block of 106th Avenue North and continued stormwater drainage installation along the 600 block of 106th Avenue North, which is anticipated through September 2023.

Asphalt paving along the 500 block and half of the 600 block of both streets was completed. The contractor continued concrete and brick paver driveway restoration along the 500 and 600 blocks of both streets as well as swale grading, cutting yard drains to grade, and irrigation system repairs. The contractor also continued road restoration activities along the 700 block of 106th Avenue North.

SYSTEMS INSTALLATION PROGRESS UPDATE
September 13, 2023

105th Avenue North

Water System Wastewater Sewer System Stormwater System
Block New Water Pipe Installation Old Water Pipe Removal New Sewer Main Installation New Sewer Laterals Installation Stormwater Installation Restoration
500 100% 100% 100% 100% 100% 92%
600 100% 50% 50% 50% 50% 40%
700 70% 0% 0% 0% 0% 0%
800 70% 0% 0% 0% 0% 0%

106th Avenue North

Water System Wastewater Sewer System Stormwater System
Block New Water Pipe Installation Old Water Pipe Removal New Sewer Main Installation New Sewer Laterals Installation Stormwater Installation Restoration
500 100% 100% 100% 100% 100% 90%
600 100% 50% 100% 100% 87% 20%
700 100% 100% 100% 100% 100% 0%
800 100% 0% 0% 0% 0% 0%

Contractor: DN Higgins, Inc
Cost: $16,767,410.00
Construction commencement date: January 2023
Anticipated construction completion date: April 2024