95th Avenue North Public Utility Renewal Project – Complete

95th Avenue North Public Utility Renewal Project map

95TH AVENUE NORTH PUBLIC UTILITY RENEWAL PROJECT

This project was part of the Naples Park Utility Renewal Project and included the repair and replacement of water, wastewater and stormwater systems that service residents and businesses along 95th Avenue North between Tamiami Trail and Vanderbilt Drive. We are pleased to announce that this portion of the project is now complete and would like to thank the residents for their patience and understanding during this time. Be advised that the Contractor’s work is covered under a one (1) year warranty until January 2021. During this time, you may see the Contractor performing warranty repairs. If you have any questions or concerns about the work, please don’t hesitate to call the Naples Park Project Information line at 239-451-0280.

SYSTEMS INSTALLATION PROGRESS UPDATE
January 15, 2020

Water System Wastewater Sewer System Stormwater System
Block New Water Pipe Installation Old Water Pipe Removal New Sewer Main Installation New Sewer Laterals Installation Stormwater Installation Restoration
500 100% 100% 100% 100% 100% 100%
600 100% 100% 100% 100% 100% 100%
700 100% 100% 100% 100% 100% 100%
800 100% 100% 100% 100% 100% 100%

Contractor: DN Higgins, Inc
Cost: $5,443,920
Construction commencement date: September 10, 2018
Construction completion date: January 10, 2020