107th Avenue North Public Utility Renewal Project – Complete

107th Avenue North Public Utility Renewal Project map

107TH AVENUE NORTH PUBLIC UTILITY RENEWAL PROJECT

This project was part of the Naples Park Utility Renewal Project and included the repair and replacement of water, wastewater and stormwater systems that service residents and businesses along 107th Avenue North between 8th Street North and Vanderbilt Drive. We are pleased to announce that this portion of the project is now complete and would like to thank the residents for their patience and understanding during this time.  Be advised that the Contractor’s work is covered under a one (1) year warranty until May 21, 2019.  During this time, you may see the Contractor performing warranty repairs. If you have any questions or concerns about the work, please don’t hesitate to call the Naples Park Project Information line at 239-839-6247.

SYSTEMS INSTALLATION PROGRESS UPDATE
May 23, 2018

Water System Wastewater Sewer System Stormwater System
New Water Pipe Installation Old  Water Pipe removal (a/c) New Gravity Sewer
System Installation
Stormwater Installation
100% 100% 100% 100%

RESTORATION PROGRESS UPDATE
May 23, 2018

107th Avenue N Block Driveways Restorations Sod Replacement Irrigation Systems Restoration
500 100% 100% 100%
600 100% 100% 100%
700 100% 100% 100%

PROJECT SCHEDULE
As per May 23, 2018

Water System Wastewater Sewer System Stormwater System Street Restoration
New Water Pipe Installation Old Water Pipe removal New Sewer Installation Stormwater Installation
 Completed  Completed Completed Completed Completed

Contractor: DN Higgins, Inc
Cost: $3,837,675
Construction commencement date: May 3, 2017
Construction completion date: May 21, 2018