108th and 109th Avenue North Public Utility Renewal Project

108th and 109th Avenue North Public Utility Renewal Project map

108th and 109th AVENUE NORTH PUBLIC UTILITY RENEWAL PROJECT

This project is part of the Naples Park Utility Renewal Project and includes the removal and replacement of water, wastewater, and stormwater infrastructure that services residents and businesses along 108th and 109th Avenues North between Tamiami Trail and Vanderbilt Drive. As part of the improvements, the contractor will be replacing water and wastewater service lines. Clay wastewater pipe laterals from the property will be replaced with new PVC pipe. This work may need to take place on private property and permission from the owner will be necessary. Stormwater collection and treatment system rehabilitation work will take place in the right of way. This project will also improve the ability to collect wastewater from Basin 101 for conveyance to the treatment facility to prevent overflows and ensure a continued high level of wastewater service to the community.

PROJECT PROGRESS UPDATE
June 15, 2022

The new water systems along both streets of 108th and 109th Avenue North have been completed, including water services, backflow preventors and water meters installation. Contractor finished new sanitary sewer main installation, lateral installation, stormwater drainage installation, road restoration, and restoration activities along the 500 block and half of the 600 block of both streets. Contractor also finished removing the existing sanitary force main along the entire length of 109th Avenue North.

Contractor finished sanitary sewer main and lateral installation along the 600 and 700 block of both streets. Contractor continued sanitary sewer main and lateral installation along the 800 block of 108th Avenue North and 8th Court East, which is anticipated to continue through June 2022. Contractor also began installing well point dewatering system along the 800 block of 109th Avenue North in anticipation of commencing sanitary sewer main and lateral installation, which is anticipated to continue through July 2022.

Contractor finished stormwater drainage installation along the 600 and 700 block of both streets and 7th Street North. Contractor will resume stormwater drainage installation along the 800 block of both streets after the new sewer main has been installed.

Contractor removed the existing asbestos-cement water main along the 600 and 700 block of both streets, and along 7h Street North. Contractor anticipates finishing asbestos-cement removal along the 800 block of both streets after they are finished replacing the sanitary sewer main and stormwater drainage.

Contractor paved the second half of the 600 block and the 700 block of both streets Contractor also finished driveway restoration activities along the 600 block of 109th Avenue North and continued driveway restoration along the 600 block of 108th Avenue North and the 700 block of both streets, which is anticipated to continue through June 2022. Contractor also continued grading the right-of-way along the 600 and 700 block of both streets.

SYSTEMS INSTALLATION PROGRESS UPDATE
June 15, 2022

108th Avenue North

Water System Wastewater Sewer System Stormwater System
Block New Water Pipe Installation Old Water Pipe Removal New Sewer Main Installation New Sewer Laterals Installation Stormwater Installation Restoration
500 100% 100% 100% 100% 100% 100%
600 100% 100% 100% 100% 100% 80%
700 100% 100% 100% 100% 100% 39%
800 100% 0% 100% 80% 0% 0%

109th Avenue North

Water System Wastewater Sewer System Stormwater System
Block New Water Pipe Installation Old Water Pipe Removal New Sewer Main Installation New Sewer Laterals Installation Existing Force Main Removal Stormwater Installation Restoration
500 100% 100% 100% 100% 100% 100% 100%
600 100% 100% 100% 100% 100% 100% 75%
700 100% 100% 100% 100% 100% 100% 45%
800 100% 0% 0% 0% N/A 0% 0%

Contractor: DN Higgins, Inc
Cost: $12,337,900.00
Construction commencement date: May 2021
Anticipated construction completion date: August 2022