108th and 109th Avenue North Public Utility Renewal Project

108th and 109th Avenue North Public Utility Renewal Project map

108th and 109th AVENUE NORTH PUBLIC UTILITY RENEWAL PROJECT

This project is part of the Naples Park Utility Renewal Project and includes the removal and replacement of water, wastewater, and stormwater infrastructure that service residents and businesses along 108th and 109th Avenues North between Tamiami Trail and Vanderbilt Drive. As part of the improvements, the contractor will be replacing water and wastewater service lines. Clay wastewater pipe laterals from the property will be replaced with new PVC pipe. This work may need to take place on private property and permission from the owner will be necessary. Stormwater collection and treatment system rehabilitation work will take place in the right of way. This project will also improve the ability to collect wastewater from Basin 101 for conveyance to the treatment facility to prevent overflows and ensure a continued high level of wastewater service to the community.

PROJECT PROGRESS UPDATE
October 13, 2021

The new water systems along the 500 and 600 block of 108th and 109th Avenue North have been completed. Contractor finished new sanitary sewer main and lateral installation along the 500 block of 108th and 109th Avenues North and began new sanitary sewer main installation along the 600 block of 109th Avenue North. Also, Contractor continued installing stormwater drainage along the north and south right-of-ways of both streets. Furthermore, Contractor began removing the existing asbestos-cement water main along the 500 block of 109th Avenue North and is anticipated to finish removing the rest of the asbestos-cement water main along the 500 block of both streets by October 2021.

Beginning on October 11, 2021, construction crews will begin wastewater improvements on the west half of the 600 blocks for both 108th and 109th Avenues North. Construction of the remainder of the stormwater improvements in the 500 and 600 blocks will continue this fall.

SYSTEMS INSTALLATION PROGRESS UPDATE
October 13, 2021

108th Avenue North

Water System Wastewater Sewer System Stormwater System
Block New Water Pipe Installation Old Water Pipe Removal New Sewer Main Installation New Sewer Laterals Installation Stormwater Installation Restoration
500 100% 50% 100% 100% 55% 0%
600 100% 0% 0% 0% 0% 0%
700 0% 0% 0% 0% 0% 0%
800 0% 0% 0% 0% 0% 0%

109th Avenue North

Water System Wastewater Sewer System Stormwater System
Block New Water Pipe Installation Old Water Pipe Removal New Sewer Main Installation New Sewer Laterals Installation Existing Force Main Removal Stormwater Installation Restoration
500 100% 50% 100% 100% 100% 50% 0%
600 100% 0% 4% 0% 100% 0% 0%
700 0% 0% 0% 0% 0% 0% 0%
800 0% 0% 0% 0% N/A 0% 0%

Contractor: DN Higgins, Inc
Cost: $12,337,900.00
Construction commencement date: May 2021
Anticipated construction completion date: August 2022