108th and 109th Avenue North Public Utility Renewal Project

108th and 109th Avenue North Public Utility Renewal Project map

108th and 109th AVENUE NORTH PUBLIC UTILITY RENEWAL PROJECT

This project is part of the Naples Park Utility Renewal Project and includes the removal and replacement of water, wastewater and stormwater infrastructure that service residents and businesses along 108th and 109th Avenues North between Tamiami Trail and Vanderbilt Drive. As part of the improvements, the contractor will be replacing water and wastewater service lines. Clay wastewater pipe laterals from the property will be replaced with new PVC pipe. This work may need to take place on private property and permission from the owner will be necessary. Stormwater collection and treatment system rehabilitation work will take place in the right of way. This project will also improve the ability to collect wastewater from Basin 101 for conveyance to the treatment facility to prevent overflows and ensure a continued high level of wastewater service to the community.

PROJECT PROGRESS UPDATE
May 5, 2021

The pre-construction meeting for the 108th and 109th Avenue North Public Utilities Renewal project was held on April 30, 2021. Collier County, Engineer of Record, CEI and Contractor personnel will perform a pre-construction walkthrough along 108th and 109th Avenues on Thursday, May 13, 2021. If additional time is needed to complete the pre-construction walkthrough it will be extended to Friday, May 14, 2021. Project construction is anticipated to commence on May 24, 2021.

SYSTEMS INSTALLATION PROGRESS UPDATE
May 5, 2021

108th Avenue North

Water System Wastewater Sewer System Stormwater System
Block New Water Pipe Installation Old Water Pipe Removal New Sewer Main Installation New Sewer Laterals Installation Stormwater Installation Restoration
500 0% 0% 0% 0% 0% 0%
600 0% 0% 0% 0% 0% 0%
700 0% 0% 0% 0% 0% 0%
800 0% 0% 0% 0% 0% 0%

109th Avenue North

Water System Wastewater Sewer System Stormwater System
Block New Water Pipe Installation Old Water Pipe Removal New Sewer Main Installation New Sewer Laterals Installation Existing Force Main Removal Stormwater Installation Restoration
500 0% 0% 0% 0% 0% 0% 0%
600 0% 0% 0% 0% 0% 0% 0%
700 0% 0% 0% 0% 0% 0% 0%
800 0% 0% 0% 0% N/A 0% 0%

Contractor: DN Higgins, Inc
Cost: $12,337,900.00
Construction commencement date: May 2021
Anticipated construction completion date: August 2022