108th and 109th Avenue North Public Utility Renewal Project

108th and 109th Avenue North Public Utility Renewal Project map

108th and 109th AVENUE NORTH PUBLIC UTILITY RENEWAL PROJECT

This project is part of the Naples Park Utility Renewal Project and includes the removal and replacement of water, wastewater and stormwater infrastructure that services residents and businesses along 108th and 109th Avenues North between Tamiami Trail and Vanderbilt Drive. As part of the improvements, the contractor will be replacing water and wastewater service lines. Clay wastewater pipe laterals from the property will be replaced with new PVC pipe. This work may need to take place on private property and permission from the owner will be necessary. Stormwater collection and treatment system rehabilitation work will take place in the right of way. This project will also improve the ability to collect wastewater from Basin 101 for conveyance to the treatment facility to prevent overflows and ensure a continued high level of wastewater service to the community.

PROJECT PROGRESS UPDATE
January 12, 2021

The new water systems along the 500 and 600 blocks of 108th and 109th Avenues North have been completed. Contractor finished new water main installation along the 700 and 800 blocks of 108th Avenue North and removal of existing asbestos-cement water main along half of the 600 block of 109th Avenue North. Contractor obtained approval of the bacteriological testing results from the Florida Department of Environmental Protection, connected the new water main along the 700 and 800 blocks of 108th Avenue North and began new water service installation along the 700 and 800 blocks of 108th Avenue North, which is anticipated to continue through January 2022. Contractor began removing the existing sanitary force main along the 700 block of 109th Avenue North in anticipation of installing the water main along the 700 and 800 blocks of 109th Avenue North.

Contractor also finished new sanitary sewer main installation, lateral installation, stormwater drainage installation, and road restoration activities along the 500 block and half of the 600 block of both streets. After water services installation has been completed the contractor will continue sanitary sewer main and stormwater drainage installation along the remaining half of the 600 block and the 700 block of 108th Avenue North. Contractor continued concrete and brick paver driveway restoration activities along the 500 block and half of the 600 block of both streets, and began right-of-way grading and restoration, which is anticipated to continue through January 2022.

SYSTEMS INSTALLATION PROGRESS UPDATE
January 12, 2021

108th Avenue North

Water System Wastewater Sewer System Stormwater System
Block New Water Pipe Installation Old Water Pipe Removal New Sewer Main Installation New Sewer Laterals Installation Stormwater Installation Restoration
500 100% 100% 100% 100% 100% 42%
600 100% 50% 50% 50% 50% 18%
700 100% 0% 0% 0% 0% 0%
800 80% 0% 0% 0% 0% 0%

109th Avenue North

Water System Wastewater Sewer System Stormwater System
Block New Water Pipe Installation Old Water Pipe Removal New Sewer Main Installation New Sewer Laterals Installation Existing Force Main Removal Stormwater Installation Restoration
500 100% 100% 100% 100% 100% 100% 39%
600 100% 50% 50% 50% 100% 50% 18%
700 0% 0% 0% 0% 50% 0% 0%
800 0% 0% 0% 0% N/A 0% 0%

Contractor: DN Higgins, Inc
Cost: $12,337,900.00
Construction commencement date: May 2021
Anticipated construction completion date: August 2022