96th Avenue North Public Utility Renewal Project – Under Construction

96th Avenue North Public Utility Renewal Project map

96TH AVENUE NORTH PUBLIC UTILITY RENEWAL PROJECT

This project is part of the Naples Park Utility Renewal Project and includes the repair and replacement of water, wastewater and stormwater systems that service residents and businesses along 96th Avenue North between Tamiami Trail and Vanderbilt Drive. As part of the improvements, the contractor will be replacing water and wastewater service lines. Clay wastewater pipe laterals from the property will be replaced with new PVC pipe. This work may need to take place on private property and permission from the owner will be necessary. Stormwater collection and treatment system rehabilitation work will take place in the right of way. This project will improve the ability to collect wastewater from Basin 101 for conveyance to the treatment facility to prevent overflows and ensure a continued high level of wastewater service for the community.

PROJECT PROGRESS UPDATE
May 20, 2020

The new water system along the 500 and 600 blocks is complete. Furthermore, the sanitary sewer system and stormwater drainage installation and existing asbestos-cement water main removal along the 500 block has also been completed. Contractor paved the roadway along the 500 block on May 6th, and is currently performing driveway restoration activities which are scheduled to be completed by May 2020, however unforeseen conditions and weather may cause that timing to change. Contractor is also scheduled to commence wastewater system installation along the 600 block by May 2020.

SYSTEMS INSTALLATION PROGRESS UPDATE
May 20, 2020

Water System Wastewater Sewer System Stormwater System
Block New Water Pipe Installation Old Water Pipe Removal New Sewer Main Installation New Sewer Laterals Installation Stormwater Installation Restoration
500 100% 100% 100% 100% 100% 31%
600 100% 0% 0% 0% 0% 0%
700 0% 0% 0% 0% 0% 0%
800 0% 0% 0% 0% 0% 0%

Contractor: DN Higgins, Inc
Cost: $5,357,500.00
Construction commencement date: January 2020
Anticipated construction completion date: February 2021