This project is part of the Naples Park Utility Renewal Project and includes the repair and replacement of water, wastewater and stormwater systems that service residents and businesses along 96th Avenue North between Tamiami Trail and Vanderbilt Drive. As part of the improvements, the contractor will be replacing water and wastewater service lines. Clay wastewater pipe laterals from the property will be replaced with new PVC pipe. This work may need to take place on private property and permission from the owner will be necessary. Stormwater collection and treatment system rehabilitation work will take place in the right of way. This project will improve the ability to collect wastewater from Basin 101 for conveyance to the treatment facility to prevent overflows and ensure a continued high level of wastewater service for the community.

PROJECT PROGRESS UPDATE
September 16, 2020

Work on the 500 block of 96th Avenue North is complete, except for the vacant lots currently being used by the Contractor as storage yards for the duration of the project. The new water, wastewater, and stormwater systems along the 600 block of 96th Avenue North are complete. Contractor completed road restoration activities, installed new stormwater drainage along 7th Street North, and is currently restoring driveways along the 600 block of 96th Avenue North. Furthermore, Contractor finished 8‐inch PVC water main installation along the 700 and 800 blocks of 96th Avenue North and successfully pressure tested and passed bacteriological testing. Contractor anticipates connecting water services along the 700 and 800 blocks in September 2020.

SYSTEMS INSTALLATION PROGRESS UPDATE
September 16, 2020

Water System Wastewater Sewer System Stormwater System
Block New Water Pipe Installation Old Water Pipe Removal New Sewer Main Installation New Sewer Laterals Installation Stormwater Installation Restoration
500 100% 100% 100% 100% 100% 100%
600 100% 98% 100% 100% 98% 38%
700 70% 0% 0% 0% 0% 0%
800 70% 0% 0% 0% 0% 0%

Contractor: DN Higgins, Inc
Cost: $5,357,500.00
Construction commencement date: January 2020
Anticipated construction completion date: February 2021