Creekside Force Main Phase 1 – Complete

Creekside phase 1 map

CREEKSIDE FORCE MAIN PHASE 1

This project consists on the installation of a new pressurized wastewater pipeline, known as a force main. This new force main will carry wastewater from the new master pump station directly to the North County Regional Water Reclamation Facility. The new pump station will be located at the intersection of 110th Avenue North and 8th Street North. It will be constructed along Creekside Boulevard from US 41 to Arthrex Boulevard. This project will improve the ability to move wastewater from Basin 101 to the wastewater treatment facility located on Goodlette Road. Phase I includes construction of force main from the intersection of Tamiami Trail North and 107th Avenue North to the proposed tie-in location at Creekside Boulevard and Arthrex Boulevard.

Contractor: DN Higgins, Inc.
Cost: $638,659.00
Construction commencement date: November 14, 2016
Construction completion date: September 10, 2017