98th and 99th Avenue North Public Utility Renewal Project

98th and 99th Avenue North Public Utility Renewal Project map

98th and 99th AVENUE NORTH PUBLIC UTILITY RENEWAL PROJECT

This project is part of the Naples Park Utility Renewal Project and includes the removal and replacement of water, wastewater and stormwater infrastructure that service residents and businesses along 98th and 99th Avenues North between Tamiami Trail and Vanderbilt Drive. As part of the improvements, the contractor will be replacing water and wastewater service lines. Clay wastewater pipe laterals from the property will be replaced with new PVC pipe. This work may need to take place on private property and permission from the owner will be necessary. Stormwater collection and treatment system rehabilitation work will take place in the right-of-way. This project will also improve the ability to collect wastewater from Basin 101 for conveyance to the treatment facility to prevent overflows and ensure a continued high level of wastewater service to the community.

PROJECT PROGRESS UPDATE
April 3, 2024

Contractor cleared the right-of-way of both 98th and 99 Avenue North in anticipation of new water main installation. Existing driveways along the right-of-way of the 500 and 600 blocks of both avenues, have been removed as well. Furthermore, the contractor finished installation of new PVC water main and water services along the 500 and 600 block of 99th Avenue North and finished water main installation activities along the 700 and 800 blocks of 99th Avenue North. The contractor also continued sanitary sewer main and laterals installation along the 500 block of 99th Avenue North.

The contractor finished installation of new water main, water services and fire hydrant assemblies along the 600 block of 98th Avenue North and successfully pressure tested and flushed the new water main. The contractor is currently chlorinating the new water main before performing bacteriological testing and connecting new water services, meters and backflow devices.

SYSTEMS INSTALLATION PROGRESS UPDATE
April 3, 2024

98th Avenue North

Water System Wastewater Sewer System Stormwater System
Block New Water Pipe Installation Old Water Pipe Removal New Sewer Main Installation New Sewer Laterals Installation Stormwater Installation Restoration
500 55% 0% 0% 0% 0% 0%
600 55% 0% 0% 0% 0% 0%
700 0% 0% 0% 0% 0% 0%
800 0% 0% 0% 0% 0% 0%

99th Avenue North

Water System Wastewater Sewer System Stormwater System
Block New Water Pipe Installation Old Water Pipe Removal New Sewer Main Installation New Sewer Laterals Installation Stormwater Installation Restoration
500 100% 0% 50% 35% 0% 0%
600 100% 0% 0% 0% 0% 0%
700 50% 0% 0% 0% 0% 0%
800 50% 0% 0% 0% 0% 0%

Contractor: DN Higgins, Inc
Cost: $17,862,085.00
Construction commencement date: January 2024
Anticipated construction completion date: July 2025