98th and 99th Avenue North Public Utility Renewal Project

98th and 99th Avenue North Public Utility Renewal Project map

98th and 99th AVENUE NORTH PUBLIC UTILITY RENEWAL PROJECT

This project is part of the Naples Park Utility Renewal Project and includes the removal and replacement of water, wastewater and stormwater infrastructure that service residents and businesses along 98th and 99th Avenues North between Tamiami Trail and Vanderbilt Drive. As part of the improvements, the contractor will be replacing water and wastewater service lines. Clay wastewater pipe laterals from the property will be replaced with new PVC pipe. This work may need to take place on private property and permission from the owner will be necessary. Stormwater collection and treatment system rehabilitation work will take place in the right-of-way. This project will also improve the ability to collect wastewater from Basin 101 for conveyance to the treatment facility to prevent overflows and ensure a continued high level of wastewater service to the community.

PROJECT PROGRESS UPDATE
July 24, 2024

The contractor cleared the right-of-way of both 98th and 99th Avenue North in anticipation of new water main installation. Existing driveways along the right-of-way of the 500 and 600 blocks of both avenues, have been removed as well. Furthermore, the contractor finished installation of new PVC water main and water services along the 500 and 600 block of both streets and finished water main installation activities along the 700 and 800 blocks of 99th Avenue North. The new water main along the 700 and 800 blocks of 99th Avenue North successfully passed the bacteriological testing and connected new water services along the 700 and 800 block.

The existing asbestos-cement water main was removed along the 500 block of both avenues and half of the 600 block of 99th Avenue North. Stormwater drainage installation was completed along the 500 block of both avenues and the 600 block of 99th Avenue North. Sanitary sewer main and laterals installation were completed along the 500 block of both avenues and the first half of the 600 block of 99th Avenue North. The contractor is currently installing sewer main, laterals, and stormwater drainage along the 600 block of 98th Avenue North. Road restoration activities were completed along the 500 and 600 block of 99th Avenue North and continued along the 500 block of 98th Avenue North. The contractor completed concrete and brick pavers driveway restoration along the 500 block and concrete driveway restoration along half of the 600 block of 99th Avenue North and is currently working on brick pavers and asphalt driveways restoration.

SYSTEMS INSTALLATION PROGRESS UPDATE
July 24, 2024

98th Avenue North

Water System Wastewater Sewer System Stormwater System
Block New Water Pipe Installation Old Water Pipe Removal New Sewer Main Installation New Sewer Laterals Installation Stormwater Installation Restoration
500 100% 100% 100% 100% 100% 10%
600 100% 0% 95% 80% 40% 0%
700 0% 0% 0% 0% 0% 0%
800 0% 0% 0% 0% 0% 0%

99th Avenue North

Water System Wastewater Sewer System Stormwater System
Block New Water Pipe Installation Old Water Pipe Removal New Sewer Main Installation New Sewer Laterals Installation Stormwater Installation Restoration
500 100% 100% 100% 100% 100% 59%
600 100% 50% 50% 50% 50% 25%
700 100% 0% 0% 0% 0% 0%
800 99% 0% 0% 0% 0% 0%

Contractor: DN Higgins, Inc
Cost: $17,862,085.00
Construction commencement date: January 2024
Anticipated construction completion date: July 2025